Jurong Synthetic Plant Turnkey Project

Project Duration : 10 months 

Peak No of Field Personal : 130

Location: Jurong Synthetic Plant

Scopes:

Mechanical Work

  • Shop fabrication

  • Site installation of new 6'' to 10'' piping with 12 000 dia-inch done

  • Site installation of structural steel and pipe bridge

 

Painting Work

  • Blasting

  • Surface preparation

  • Thermal Spray Aluminium(TSA)

 

Scaffolding Work

  • Erecting 24000m^3 of scaffold within 10 weeks

Having a dedicated & committed team working hand in hand to ensure a smooth and safe operation being carried out. These are just example of how SLE works to deliver the best result for our client.