Flare Replacement

Project Duration: 2 months

Peak No of Field Personal: 120

Location: PAC

Turnkey contractor for Flare Works during plant shutdown.

- Flare Tip Replacement: Remove existing flare tip and installed new flare tip at 100m height.

- End to end Piping Works: Replaced and installed more than 900 meters worth of pipes (30'' diameter). Scope includes shop pipe fabrication to site installation.

- Scaffold Erection: Erected approximately 20,000 m3 of scaffold materials to augment mechanical site works, including vertical scaffold erection at height to enable Flare Tip replacement.